TITLE 16. ECONOMIC REGULATION

PART 2. PUBLIC UTILITY COMMISSION OF TEXAS

CHAPTER 24. SUBSTANTIVE RULES APPLICABLE TO WATER AND SEWER SERVICE PROVIDERS

SUBCHAPTER H. CERTIFICATES OF CONVENIENCE AND NECESSITY

16 TAC §24.245, §24.259

The Public Utility Commission of Texas (commission) adopts amendments to §24.245, relating to Revocation of a Certificate of Convenience and Necessity or Amendment of a Certificate of Convenience and Necessity by Decertification, Expedited Release or Streamlined Expedited Release, and §24.259, relating to Single Certification in Incorporated or Annexed Areas, with changes to the proposed text as published in the April 10, 2026 issue of the Texas Register (51 TexReg 2300). The rules will be republished.

Amendments to §24.245 establish requirements for an expedited release and a streamlined expedited release petitioner to submit a report to the commission, which verifies that the petitioner paid compensation to the former certificate of convenience and necessity (CCN) holder. Amendments to §24.259 implement the following process and procedural modifications: establishes requirements for a municipality or franchised utility to submit a report to the commission verifying that compensation was paid by it to the former retail public utility; replaces the requirement for the commission to determine compensation for former retail public utility property rendered useless or valueless by single certification with a requirement to determine just and adequate compensation for adverse effects on property remaining in former utility's ownership; and requires that appeals against a final order of the commission granting single certification to a municipality must be filed with the commission before seeking further review. Additionally, clarifying and consistency edits were made to the rule language, including non-substantive revisions to a definition to improve clarity. The amendments are adopted under Project Number 59332.

The commission did not receive public comments on the proposed amendments.

The amendments are adopted under TWC §13.041(a), which provides the commission the general power to regulate and supervise the business of each public utility within its jurisdiction and to do anything specifically designated or implied by the TWC that is necessary and convenient to the exercise of that power and jurisdiction; TWC §13.041(b), which provides the commission with the authority to adopt and enforce rules reasonably required in the exercise of its powers and jurisdiction; TWC §13.254(a-3), which provides the commission the authority to require the reporting of compensation paid by the petitioner to the decertified retail public utility; TWC §13.2541(f), which provides the commission the authority to require the reporting of compensation paid by the petitioner to the CCN holder; TWC §13.255(c-1), which provides the commission the authority to require the reporting of adequate and just compensation paid by the municipality or franchised utility to the former retail public utility; and TWC §13.255(c-3), which authorizes a retail public utility to appeal a final order of the commission granting single certification to a municipality.

Cross Reference to Statutes: Texas Water Code §13.041(a); §13.041(b); §13.254(a-3); §13.2541(f); §13.255(c-1); and §13.255(c-3).

§24.245. Revocation of a Certificate of Convenience and Necessity or Amendment of a Certificate of Convenience and Necessity by Decertification, Expedited Release, or Streamlined Expedited Release.

(a) Applicability. This section applies to proceedings for revocation or amendment by decertification, expedited release, or streamlined expedited release of a certificate of convenience and necessity (CCN).

(b) Definitions. The following terms, when used in this section, have the following meanings unless the context indicates otherwise:

(1) Alternate retail public utility--The retail public utility from which a landowner plans to receive service after the landowner obtains expedited release under subsection (f) of this section.

(2) Amendment--The change of a CCN to remove a portion of a service area by decertification amendment, expedited release, or streamlined expedited release.

(3) Current CCN holder--An entity that currently holds a CCN to provide service to an area for which revocation or amendment is sought.

(4) Decertification amendment--A process by which a portion of a certificated service area is removed from a CCN, other than expedited release or streamlined expedited release.

(5) Expedited Release--Removal of a tract of land from a CCN area under Texas Water Code (TWC) §13.254(a-1).

(6) Former CCN holder--An entity that formerly held a CCN to provide service to an area that was removed from the entity's service area by revocation or amendment.

(7) Landowner--The owner of a tract of land who files a petition for expedited release or streamlined expedited release.

(8) Prospective retail public utility--A retail public utility seeking to provide service to a removed area.

(9) Removed area--Area that will be or has been removed under this section from a CCN.

(10) Streamlined Expedited Release--Removal of a tract of land from a CCN area under TWC §13.2541.

(c) Provisions applicable to all proceedings for revocation, decertification amendment, expedited release, or streamlined expedited release.

(1) An order of the commission issued under this section does not transfer any property, except as provided under subsection (l) of this section.

(2) A former CCN holder is not required to provide service within a removed area.

(3) If the CCN of any retail public utility is revoked or amended by decertification, expedited release, or streamlined expedited release, the commission may by order require one or more other retail public utilities to provide service to the removed area, but only with the consent of each retail public utility that is to provide service.

(4) A retail public utility, including an alternate retail public utility, may not in any way render retail water or sewer service directly or indirectly to the public in a removed area unless any compensation due has been paid to the former CCN holder and a CCN to serve the area has been obtained, if one is required.

(d) Revocation or amendment by decertification.

(1) At any time after notice and opportunity for hearing, the commission may revoke any CCN or amend any CCN by decertifying a portion of the service area if the commission finds that any of the circumstances identified in this paragraph exist.

(A) The current CCN holder has never provided, is no longer providing, is incapable of providing, or has failed to provide continuous and adequate service in all or part of the certificated service area. If the current CCN holder opposes revocation or decertification amendment on one of these bases, it has the burden of proving that it is, or is capable of, providing continuous and adequate service.

(B) The current CCN holder is in an affected county as defined in TWC §16.341, and the cost of providing service by the current CCN holder is so prohibitively expensive as to constitute denial of service. Absent other relevant factors, for commercial developments or residential developments started after September 1, 1997, the fact that the cost of obtaining service from the current CCN holder makes the development economically unfeasible does not render such cost prohibitively expensive.

(C) The current CCN holder has agreed in writing to allow another retail public utility to provide service within its certificated service area or a portion of its service area, except for an interim period, without amending its CCN.

(D) The current CCN holder failed to apply for a cease-and-desist order under TWC §13.252 and §24.255 of this title (relating to Content of Request for Cease and Desist Order by the Commission under TWC §13.252) within 180 days of the date that the current CCN holder became aware that another retail public utility was providing service within the current CCN holder's certificated service area, unless the current CCN holder proves that good cause exists for its failure to timely apply for a cease-and-desist order.

(E) The current CCN holder has consented in writing to the revocation or amendment.

(2) A retail public utility may file a written request with the commission to revoke its CCN or to amend its CCN by decertifying a portion of the service area.

(A) The retail public utility must provide, at the time its request is filed, notice of its request to each customer and landowner within the affected service area of the utility.

(B) The request must specify the area that is requested to be revoked or removed from the CCN area.

(C) The request must address the effect of the revocation or decertification amendment on the current CCN holder, any existing customers, and landowners in the affected service area.

(D) The request must include the mapping information required by §24.257 of this title (relating to Mapping Requirements for Certificate of Convenience and Necessity Applications).

(E) The commission may deny the request to revoke or amend a CCN if existing customers or landowners will be adversely affected.

(F) If a retail public utility's request for decertification amendment or revocation by consent under this paragraph is granted, the retail public utility is not entitled to compensation from a prospective retail public utility.

(3) The commission may initiate a proceeding to revoke a CCN or decertify a portion of a service area on its own motion or upon request of commission staff.

(4) The current CCN holder has the burden to establish that it is, or is capable of, providing continuous and adequate service and, if applicable, that there is good cause for failing to file a cease and desist action under TWC §13.252 and §24.255 of this title.

(e) Decertification amendment for a municipality's service area. After notice to a municipality and an opportunity for a hearing, the commission may decertify an area that is located outside the municipality's extraterritorial jurisdictional boundary if the municipality has not provided service to the area on or before the fifth anniversary of the date the CCN was granted for the area. This subsection does not apply to an area that was transferred to a municipality's certificated service area by the commission and for which the municipality has spent public funds.

(1) A proceeding to remove an area from a municipality's service area may be initiated by the commission with or without a petition.

(2) A petition filed under this subsection must allege that a CCN was granted for the area more than five years before the petition was filed and the municipality has not provided service in the area.

(3) A petition filed under this subsection must include the mapping information required by §24.257 of this title.

(4) Notice of the proceeding to remove an area must be given to the municipality, landowners within the area to be removed, and other retail public utilities as determined by the presiding officer.

(5) If the municipality asserts that it is providing service to the area, the municipality has the burden to prove that assertion.

(f) Expedited release.

(1) An owner of a tract of land may petition the commission for expedited release of all or a portion of the tract of land from a current CCN holder's certificated service area so that the area may receive service from an alternate retail public utility if all the following circumstances exist:

(A) the tract of land is at least 50 acres in size;

(B) the tract of land is not located in a platted subdivision actually receiving service;

(C) the landowner has submitted a request for service to the current CCN holder at least 90 calendar days before filing the petition;

(D) the alternate retail public utility possesses the financial, managerial, and technical capability to provide service as identified in the request for service provided under paragraph (5) of this subsection on a continuous and adequate basis; and

(E) the current CCN holder:

(i) has refused to provide service;

(ii) cannot provide service as identified in the request for service provided under paragraph (5) of this subsection on a continuous and adequate basis; or

(iii) conditions the provision of service on the payment of costs not properly allocable directly to the landowner's service request, as determined by the commission.

(2) An owner of a tract of land may not file a petition under paragraph (1) of this subsection if the landowner's property is located in the boundaries of any municipality or the extraterritorial jurisdiction of a municipality with a population of more than 500,000 and the municipality or retail public utility owned by the municipality is the current CCN holder.

(3) The landowner's desired alternate retail public utility must be:

(A) an existing retail public utility; or

(B) a district proposed to be created under article 16, §59 or article 3, §52 of the Texas Constitution.

(4) The fact that a current CCN holder is a borrower under a federal loan program does not prohibit the filing of a petition under this subsection or authorizing an alternate retail public utility to provide service to the removed area.

(5) The landowner must submit to the current CCN holder a written request for service. The request must be sent by certified mail, return receipt requested, or by hand delivery with written acknowledgement of receipt. For a request other than for standard residential or commercial service, the written request must identify the following:

(A) the tract of land or portion of the tract of land for which service is sought;

(B) the time frame within which service is needed for current and projected service demands in the tract of land;

(C) the reasonable level and manner of service needed for current and projected service demands in the area;

(D) the approximate cost for the alternate retail public utility to provide service at the same level, and in the same manner, that is requested from the current CCN holder;

(E) the flow and pressure requirements and specific infrastructure needs, including line size and system capacity for the required level of fire protection requested, if any; and

(F) any additional information requested by the current CCN holder that is reasonably related to determining the capacity or cost of providing service at the level, in the manner, and in the time frame, requested.

(6) The landowner's petition for expedited release under this subsection must be verified by a notarized affidavit and demonstrate that the circumstances identified in paragraph (1) of this subsection exist. The petition must include the following:

(A) the name of the alternate retail public utility;

(B) a copy of the request for service submitted as required by paragraph (5) of this subsection;

(C) a copy of the current CCN holder's response to the request for service, if any;

(D) copies of deeds demonstrating ownership of the tract of land by the landowner; and

(E) the mapping information described in subsection (k) of this section.

(7) The landowner must mail a copy of the petition to the current CCN holder and the alternate retail public utility via certified mail on the day that the landowner files the petition with the commission.

(8) The presiding officer will determine whether the petition is administratively complete. If the petition is determined not to be administratively complete, the presiding officer will issue an order describing the deficiencies in the petition and setting a deadline for the petitioner to address the deficiencies. When the petition is determined to be administratively complete, the presiding officer will establish a procedural schedule that is consistent with paragraphs (9) and (10) of this subsection. The presiding officer may recommend dismissal of the petition under §22.181(d) of this title if the petitioner fails to supplement or amend the petition within the required timeframe after the presiding officer has determined that the petition is not administratively complete.

(9) The current CCN holder may file a response to the petition within a timeframe specified by the presiding officer, not to exceed 20 days from the date the petition is determined to be administratively complete. The response must be verified by a notarized affidavit.

(10) The commission will grant the petition within 60 calendar days from the date the petition was found to be administratively complete unless the commission makes an express finding that the landowner failed to satisfy all of the requirements of this subsection and makes separate findings of fact and conclusions of law for each requirement based solely on the information provided by the landowner and the current CCN holder. The commission may condition the granting or denial of a petition on terms and conditions specifically related to the landowner's service request and all relevant information submitted by the landowner, the current CCN holder, and commission staff.

(11) The commission will base its decision on the filings submitted by the current CCN holder, the landowner, and commission staff. Chapter 2001 of the Texas Government Code does not apply to any petition filed under this subsection. The current CCN holder or landowner may file a motion for rehearing of the commission's decision on the same timeline that applies to other final orders of the commission. The commission's order ruling on the petition may not be appealed.

(12) If the current CCN holder has never made service available through planning, design, construction of facilities, or contractual obligations to provide service to the tract of land, the commission is not required to find that the alternate retail public utility can provide better service than the current CCN holder, but only that the alternate retail public utility can provide the requested service. This paragraph does not apply to Cameron, Willacy, and Hidalgo Counties or to a county that meets any of the following criteria:

(A) the county has a population of more than 30,000 and less than 36,000 and borders the Red River;

(B) the county has a population of more than 100,000 and less than 200,000 and borders a county described by subparagraph (A) of this paragraph;

(C) the county has a population of 170,000 or more and is adjacent to a county with a population of 1.5 million or more that is within 200 miles of an international border; or

(D) the county has a population of more than 40,000 and less than 50,000 and contains a portion of the San Antonio River.

(13) If the alternate retail public utility is a proposed district, then the commission will condition the release of the tract of land and required CCN amendment or revocation on the final and unappealable creation of the district. The district must file a written notice with the commission when the creation is complete and provide a copy of the final order, judgment, or other document creating the district.

(14) The commission may require an award of compensation to the former CCN holder under subsection (g) of this section. The determination of the amount of compensation, if any, will be made according to the procedures in subsection (g) of this section.

(15) If the commission requires an award of compensation to the former CCN holder, the petitioner must file a report verifying that the full amount of compensation has been paid to the former CCN holder. The report must be filed in the same docket in which compensation was awarded within 30 days of payment of compensation.

(g) Determination of compensation to former CCN holder after revocation, decertification amendment or expedited release. The determination of the monetary amount of compensation to be paid to the former CCN holder, if any, will be determined at the time another retail public utility seeks to provide service in the removed area and before service is actually provided. This subsection does not apply to revocations or decertification amendments under subsection (d)(2) of this section or to streamlined expedited release under subsection (h) of this section.

(1) After the commission has issued its order granting revocation, decertification, or expedited release, the prospective retail public utility must file a notice of intent to provide service. A notice of intent filed before the commission issues its order under subsection (d) or (f) of this section is deemed to be filed on the date the commission's order is signed.

(2) The notice of intent must include the following information:

(A) a statement that the filing is a notice of intent to provide service to an area that has been removed from a CCN under subsection (d) or (f) of this section;

(B) the name and CCN number of the former CCN holder; and

(C) whether the prospective retail public utility and former CCN holder have agreed on the amount of compensation to be paid to the former CCN holder.

(3) If the former CCN holder and prospective retail public utility have agreed on the amount of compensation to be paid to the former CCN holder, they must make a joint filing with the commission within 60 days of the filing of the notice of intent to provide service. The filing must state the amount of the compensation to be paid.

(4) If the former CCN holder and prospective retail public utility have not agreed on the compensation to be paid to the former CCN holder, the monetary amount of compensation must be determined by a qualified individual or firm serving as an independent appraiser as follows:

(A) If the former CCN holder and prospective retail public utility have agreed on an independent appraiser, they must make a joint filing with the commission identifying the individual or firm who will be the independent appraiser and must file its appraisal with the commission within 60 days of the filing of the notice of intent. The costs of the independent appraiser must be borne by the prospective retail public utility.

(B) If the former CCN holder and prospective retail public utility cannot agree on an independent appraiser within ten days of the filing of the notice of intent, the former CCN holder and prospective retail public utility must each engage its own appraiser at its own expense. Each appraiser must file its appraisal with the commission within 60 days of the filing of the notice of intent. After receiving the appraisals, the commission will appoint a third appraiser who must make a determination of compensation within 30 days. The determination by the commission-appointed appraiser may not be less than the lower appraisal or more than the higher appraisal of the appraisers engaged by the former CCN holder and prospective retail public utility. The former CCN holder and prospective retail public utility must each pay half the cost of the commission-appointed appraisal directly to the commission-appointed appraiser.

(C) The appraisers must determine the amount of compensation in accordance with subsection (j) of this section.

(5) The determination of compensation by the agreed-upon appraiser under paragraph (4)(A) of this subsection or the commission-appointed appraiser under paragraph (4)(B) of this subsection is binding on the commission, the landowner, the former CCN holder, and the prospective retail public utility.

(6) If the former CCN holder fails to make a filing with the commission about the amount of agreed compensation, or to engage an appraiser, or to file an appraisal within the timeframes required by this subsection, the amount of compensation to be paid will be deemed to be zero. If the prospective retail public utility fails to make a filing with the commission about the amount of agreed compensation, or to engage an appraiser, or to file an appraisal within the timeframes required by this subsection, the presiding officer may recommend denial of the notice of intent to provide service to the removed area.

(7) The commission will issue an order establishing the amount of compensation to be paid to the former CCN holder not later than 90 days after the date on which a retail public utility files its notice of intent to provide service to the decertified area.

(h) Streamlined expedited release.

(1) The owner of a tract of land may petition the commission for streamlined expedited release of all or a portion of the tract of land from the current CCN holder's certificated service area if all the following conditions are met:

(A) the tract of land is at least 25 acres in size;

(B) the tract of land is not receiving service of the type that the current CCN holder is authorized to provide under the applicable CCN; and

(C) at least part of the tract of land is located in the current CCN holder's certificated service area and at least some of that part is located in a qualifying county.

(2) A qualifying county under paragraph (1)(C) of this subsection:

(A) has a population of at least 1.2 million;

(B) is adjacent to a county with a population of at least 1.2 million, and does not have a population of more than 50,500 and less than 52,000; or

(C) has a population of more than 200,000 and less than 233,500 and does not contain a public or private university that had a total enrollment in the most recent fall semester of 40,000 or more.

(3) A landowner seeking streamlined expedited release under this subsection must file with the commission a petition and supporting documentation containing the following information and verified by a notarized affidavit:

(A) a statement that the petition is being submitted under TWC §13.2541 and this subsection;

(B) proof that the tract of land is at least 25 acres in size;

(C) proof that at least part of the tract of land is located in the current CCN holder's certificated service area and at least some of that part is located in a qualifying county;

(D) a statement of facts that demonstrates that the tract of land is not currently receiving service;

(E) copies of deeds demonstrating ownership of the tract of land by the landowner;

(F) proof that a copy of the petition was mailed to the current CCN holder via certified mail on the day that the landowner filed the petition with the commission; and

(G) the mapping information described in subsection (k) of this section.

(4) The presiding officer will determine whether the petition is administratively complete. If the petition is determined not to be administratively complete, the presiding officer will issue an order describing the deficiencies in the petition and setting a deadline for the petitioner to address the deficiencies. When the petition is determined to be administratively complete, the presiding officer will establish a procedural schedule that is consistent with paragraphs (5) and (6) of this subsection. The presiding officer may recommend dismissal of the petition if the petitioner fails to supplement or amend the petition within the required timeframe after the presiding officer has determined that the petition is not administratively complete.

(5) The current CCN holder may file a response to the petition within a timeframe specified by the presiding officer, not to exceed 20 days from the date the petition is determined to be administratively complete. The response must be verified by a notarized affidavit.

(6) The commission will issue a decision on a petition filed under this subsection no later than 60 calendar days after the presiding officer by order determines that the petition is administratively complete. The commission will base its decision on the information filed by the landowner, the current CCN holder, and commission staff. No hearing will be held.

(7) The fact that a current CCN holder is a borrower under a federal loan program is not a bar to the release of a tract of land under this subsection. The CCN holder must not initiate an application to borrow money under a federal loan program after the date the petition is filed until the commission issues a final decision on the petition.

(8) The commission may require an award of compensation by the landowner to the former CCN holder as specified in subsection (i) of this section.

(9) If the commission requires an award of compensation to the former CCN holder, the petitioner must file a report verifying that the full amount of compensation has been paid to the former CCN holder. The report must be filed in the same docket in which compensation was awarded within 30 days of payment of compensation.

(i) Determination of compensation to former CCN holder after streamlined expedited release. The amount of compensation, if any, will be determined after the commission has granted a petition for streamlined expedited release filed under subsection (h) of this section. The amount of compensation, if any, will be decided in the same proceeding as the petition for streamlined expedited release.

(1) If the former CCN holder and landowner have agreed on the amount of compensation to be paid to the former CCN holder, they must make a joint filing with the commission within 70 days after the commission has granted streamlined expedited release. The filing must state the amount of the compensation to be paid.

(2) If the former CCN holder and landowner have not agreed on the compensation to be paid to the former CCN holder, the monetary amount of compensation must be determined by a qualified individual or firm serving as an independent appraiser under the following procedure.

(A) If the former CCN holder and landowner have agreed on an independent appraiser, the former CCN holder and landowner must make a joint filing with the commission identifying the individual or firm who will be the independent appraiser after the commission grants streamlined expedited release under subsection (h) of this section. The costs of the independent appraiser must be borne by the landowner. The appraiser must file its appraisal with the commission within 70 days after the commission grants streamlined expedited release.

(B) If the former CCN holder and landowner have not agreed on an independent appraiser within ten days after the commission grants streamlined expedited release under subsection (h) of this section, the former CCN holder and landowner must each engage its own appraiser at its own expense. Each appraiser must file its appraisal with the commission within 70 calendar days after the commission grants streamlined expedited release. After receiving the appraisals, the commission will appoint a third appraiser who must make a determination of compensation within 100 days after the date the commission grants streamlined expedited release. The determination by the commission-appointed appraiser may not be less than the lower appraisal or more than the higher appraisal made by the appraisers engaged by the former CCN holder and landowner. The former CCN holder and landowner must each pay half the cost of the commission-appointed appraisal directly to the commission-appointed appraiser.

(C) The appraisers must determine the amount of compensation in accordance with subsection (j) of this section.

(3) The determination of compensation by the agreed-upon appraiser under paragraph (2)(A) of this subsection or the commission-appointed appraiser under paragraph (2)(B) of this subsection is binding on the commission, former CCN holder, and landowner.

(4) If the former CCN holder fails to make a filing with the commission about the amount of agreed compensation, or engage an appraiser, or file an appraisal within the timeframes required by this subsection, the amount of compensation to be paid will be deemed to be zero. If the landowner fails to make a filing with the commission about the amount of agreed compensation, or engage an appraiser, or file an appraisal within the timeframes required by this subsection, the commission will base the amount of compensation to be paid on the appraisal provided by the CCN holder.

(5) The commission will issue an order establishing the amount of compensation to be paid and directing the landowner to pay the compensation to the former CCN holder not later than 60 days after the commission receives the final appraisal.

(6) The landowner must pay the compensation to the former CCN holder not later than 90 days after the date the compensation amount is determined by the commission. The commission will not authorize a prospective retail public utility to serve the removed area until the landowner has paid to the former CCN holder any compensation that is required.

(j) Valuation of real and personal property of the former CCN holder.

(1) The value of real property must be determined according to the standards set forth in chapter 21 of the Texas Property Code governing actions in eminent domain.

(2) The value of personal property must be determined according to this paragraph. The following factors must be used in valuing personal property:

(A) the amount of the former CCN holder's debt allocable to service to the removed area;

(B) the value of the service facilities belonging to the former CCN holder that are located within the removed area;

(C) the amount of any expenditures for planning, design, or construction of the service facilities of the former CCN holder that are allocable to service to the removed area;

(D) the amount of the former CCN holder's contractual obligations allocable to the removed area;

(E) any demonstrated impairment of service or any increase of cost to consumers of the former CCN holder remaining after a CCN revocation or amendment under this section;

(F) the impact on future revenues lost from existing customers;

(G) necessary and reasonable legal expenses and professional fees, including costs incurred to comply with TWC §13.257(r); and

(H) any other relevant factors as determined by the commission.

(k) Mapping information.

(1) For proceedings under subsections (f) or (h) of this section, the following mapping information must be filed with the petition:

(A) a general-location map identifying the tract of land in reference to the nearest county boundary, city, or town;

(B) a detailed map identifying the tract of land in reference to verifiable man-made and natural landmarks, such as roads, rivers, and railroads. If ownership of the tract of land is conveyed by multiple deeds, this map must also identify the location and acreage of land conveyed by each deed; and

(C) one of the following for the tract of land:

(i) a metes-and-bounds survey sealed or embossed by either a licensed state land surveyor or a registered professional land surveyor;

(ii) a recorded plat; or

(iii) digital mapping data in a shapefile (SHP) format georeferenced in either NAD 83 Texas State Plane Coordinate System (US feet) or in NAD 83 Texas Statewide Mapping System (meters). The digital mapping data must include a single, continuous polygon record.

(D) a written and signed attestation confirming that the representative responsible for creating the mapping information has reviewed the commission's online mapping resources on the commission's CCN Mapping Resources webpage, including all video files. The attestation must be in the following format: "I, {name}, serve as {employment title} of {applicant name}. I am responsible for creating mapping information required for this application. Before submitting mapping information in conjunction with the application, I reviewed the mapping resources on the Public Utility Commission's CCN Mapping Resources webpage, including all video files."

(2) Commission staff may request additional mapping information.

(3) All maps must be filed in accordance with §22.71 and §22.72 of this title (relating to Filing of Pleadings, Documents and Other Materials and Formal Requisites of Pleadings and Documents to be filed with the Commission, respectively).

(l) Additional conditions for decertification under subsection (d) of this section.

(1) If the current CCN holder did not agree in writing to a revocation or amendment by decertification under subsection (d) of this section, then an affected retail public utility may request that the revocation or amendment be conditioned on the following:

(A) ordering the prospective retail public utility to provide service to the entire service area of the current CCN holder; and

(B) transferring the entire CCN of the current CCN holder to the prospective retail public utility.

(2) If the commission finds that, as a result of revocation or amendment by decertification under subsection (d) of this section, the current CCN holder will be unable to provide continuous and adequate service at an affordable cost to the current CCN holder's remaining customers, then:

(A) the commission will order the prospective retail public utility to provide continuous and adequate service to the remaining customers at a cost comparable to the cost of that service to the prospective retail public utility's other customers and will establish the terms under which service must be provided; and

(B) the commission may order any of the following terms:

(i) transfer of debt and other contract obligations;

(ii) transfer of real and personal property;

(iii) establishment of interim rates for affected customers during specified times; and

(iv) other provisions necessary for the just and reasonable allocation of assets and liabilities.

(3) The prospective retail public utility must not charge the affected customers any transfer fee or other fee to obtain service, except for the following:

(A) the prospective retail public utility's usual and customary rates for monthly service, or

(B) interim rates set by the commission, if applicable.

(4) If the commission orders the prospective retail public utility to provide service to the entire service area of the current CCN holder, the commission will not order compensation to the current CCN holder, the commission will not make a determination of the amount of compensation to be paid to the current CCN holder, and the prospective retail public utility must not file a notice of intent under subsection (g) of this section.

§24.259. Single Certification in Incorporated or Annexed Areas.

(a) Applicability. This section applies to a requested area that also meets the following criteria:

(1) the requested area has been incorporated or annexed by a municipality;

(2) a retail public utility provides service to the requested area under a certificate of convenience and necessity (CCN); and

(3) the retail public utility that holds the CCN under which the requested area is currently certificated is one of the following:

(A) a water supply or sewer service corporation, a special utility district under chapter 65 of the Texas Water Code, or a fresh water supply district under chapter 53 of the Texas Water Code; or

(B) not a water supply or sewer service corporation, and its service area is located entirely within the boundaries of a municipality that has a population of at least 1.7 million according to the most recent federal census.

(b) Definitions. In this section, the following words and terms have the definitions provided by this subsection.

(1) Impaired property--Property remaining in the ownership of the current CCN holder after single certification that would sustain damages from or be adversely affected by the transfer of property to the municipality.

(2) Franchised utility--A retail public utility that has been granted a franchise by a municipality to provide service inside the municipal boundaries.

(3) Current CCN holder--The retail public utility that holds a CCN to provide service to the municipality's requested area.

(4) Requested property--Property that the municipality has requested in its application be transferred to it or to a franchised utility from the current CCN holder, which request is solely for application purposes and does not, by itself, effectuate an actual transfer.

(c) Notice of intent to provide service in incorporated or annexed area. A municipality that intends to provide service itself or through a franchised utility to all or part of an annexed or incorporated area must notify the current CCN holder in writing of the municipality's intent. The written notice to the current CCN holder must specify the following information:

(1) the municipality's requested area;

(2) any requested property;

(3) the municipal ordinance or other action that annexed or incorporated the municipality's requested area;

(4) what kind of service will be provided;

(5) whether a municipally owned utility or franchised utility will provide the service; and

(6) the municipally owned utility's or the franchised utility's identity and contact information.

(d) Written agreement regarding service to area. The municipality and the current CCN holder may agree in writing that all or part of the area incorporated or annexed by the municipality may receive service from a municipally owned utility, a franchised utility, or the current CCN holder, or any combination of those entities.

(1) If a franchised utility is to provide service to any part of the area, the franchised utility must also be a party to the agreement.

(2) The executed agreement may provide for single or dual certification of all or part of the area incorporated or annexed by the municipality, for the purchase of facilities or property, and may contain any other terms agreed to by the parties.

(3) The executed agreement must be filed with the commission. The commission must incorporate the agreement's terms into the respective CCNs of the municipality, current CCN holder, and franchised utility, as appropriate.

(e) Application for single certification. If an agreement is not executed within 180 calendar days after the municipality provides written notice under subsection (c) of this section and the municipality intends to provide service to the municipality's requested area, the municipality must submit an application to the commission to grant single certification to a municipally owned utility or a franchised utility.

(1) If a franchised utility will provide service to any part of the municipality's requested area, the franchised utility must join the application.

(2) The application must include all of the information listed in this paragraph.

(A) The application must identify the municipal ordinance or other action that annexed or incorporated the municipality's requested area.

(B) The application must identify the type of service that will be provided to the municipality's requested area.

(C) The application must identify the municipally owned utility or franchised utility that will provide service to the municipality's requested area and, if each will serve part of the area, the area that each will serve.

(D) The application must identify contact information for the current CCN holder.

(E) The application must demonstrate compliance with the TCEQ's minimum requirements for public drinking water systems if the municipality owns a public drinking water system.

(F) The application must demonstrate that at least 180 calendar days have passed since the date that the municipality provided written notice under subsection (c) of this section.

(G) The application must identify with specificity any property that the municipality requests be transferred from the current CCN holder.

(H) The application must identify the boundaries of the municipality's incorporated area or extraterritorial jurisdiction by providing digital-mapping data in a shapefile (SHP) format georeferenced in either NAD 83 Texas State Plane Coordinate System (US feet) or in NAD 83 Texas Statewide Mapping System (meters). The digital mapping data must include a single, continuous polygon record.

(I) The application must identify the municipality's requested area by providing mapping information to clearly identify the area the municipality is seeking in accordance with §24.257 of this title relating to Mapping Requirements for Certificate of Convenience and Necessity Application. Commission staff may request additional mapping information after the application is submitted.

(3) Within 30 calendar days of the filing of the application, commission staff must file a recommendation regarding whether the application meets the requirements of this subsection.

(f) Notices for single-certification application. The applicant must send a copy of the application to the current CCN holder by certified mail or hand-delivery on the same day that the applicant submits the application to the commission.

(g) Response to single-certification application. The current CCN holder must file a response to the application for single certification in conformance with this subsection.

(1) The response must be filed within 40 calendar days of the filing of the application.

(2) The response must state the following information:

(A) whether the single certification is agreed to; and

(B) if there is no agreement for single certification, any conditions that, if met, would cause the current CCN holder to agree to single certification.

(3) In its response, the current CCN holder must identify any impaired property that would result from certification of the municipality's requested area to the municipality.

(4) There is a rebuttable presumption that there is no impaired property if the current CCN holder fails to timely respond as required under paragraph (1) of this subsection. Upon motion and proof of service consistent with the requirements of subsection (f) of this section, the presiding officer may issue an order determining that there is no impaired property.

(h) Referral to SOAH.

(1) Within 50 calendar days of the filing of the application, a presiding officer must determine whether an application for single certification meets the requirements of subsection (e) of this section.

(2) If the presiding officer determines that the application meets the requirements of subsection (e) of this section, the application must be referred to the State Office of Administrative Hearings (SOAH) for a hearing. SOAH must fix a time and place for a hearing on the application and must notify the current CCN holder, municipality, and franchised utility, if any, of the hearing.

(3) Except as provided under paragraph (4) of this subsection, if the presiding officer determines that the application does not meet the requirements of subsection (e) of this section, the applicant must supplement its application to correct the identified deficiencies within a timeframe, and under a process, established by the presiding officer.

(4) The application must be denied if the municipality fails to demonstrate compliance with the TCEQ's minimum requirements for public drinking water systems. This paragraph does not apply to a municipality that does not own a public drinking water system.

(i) Hearing at SOAH.

(1) The hearing at SOAH must be limited to determining what property, if any, is impaired property or requested property.

(2) The current CCN holder bears the burden of proof to demonstrate what property is impaired property.

(3) The requested property must be limited to the specific property identified in the application.

(4) The SOAH administrative law judge must issue a proposal for decision for the commission's consideration.

(j) Interim order. The commission must issue an interim order identifying what property, if any, is impaired property or requested property.

(k) Administrative Completeness. Section 24.8 of this title relating to Administrative Completeness does not apply to the determination of administrative completeness under this section. After the commission has issued its interim order under subsection (j) of this section, a presiding officer must determine whether the application for single certification is administratively complete and must establish a procedural schedule that will allow total compensation for any property identified in the interim order to be determined not later than 90 calendar days after the application is determined to be administratively complete.

(l) Valuation of real property. The value of real property that the commission identified in the interim order issued under subsection (j) of this section must be determined according to the standards set forth in Texas Property Code, chapter 21, governing actions in eminent domain.

(m) Valuation of personal property. The value of personal property that the commission identified in the interim order issued under subsection (j) of this section must be determined according to this subsection.

(1) This subsection is intended to ensure that the compensation to a current CCN holder is just and adequate as provided by these rules.

(2) The following factors must be used to value personal property that the commission identified in the interim order issued under subsection (j) of this section:

(A) the impact on the current CCN holder's existing indebtedness and the current CCN holder's ability to repay that debt;

(B) the value of the current CCN holder's service facilities located within the municipality's requested area;

(C) the amount of any expenditures for planning, design, or construction of service facilities outside the incorporated or annexed area that are allocable to service to the municipality's requested area;

(D) the amount of the current CCN holder's contractual obligations allocable to the municipality's requested area;

(E) any demonstrated impairment of service or increase of cost to the current CCN holder's customers that remain after the single certification;

(F) the impact on future revenues lost from existing customers;

(G) necessary and reasonable legal expenses and professional fees;

(H) factors relevant to maintaining the current financial integrity of the current CCN holder; and

(I) other relevant factors as determined by the commission.

(n) Valuation Process.

(1) For an area incorporated by a municipality, the valuation of property that the commission identified in the interim order issued under subsection (j) of this section must be determined by a qualified individual or firm serving as an independent appraiser. The independent appraiser must be limited to appraising the property that the commission identified in the interim order issued under subsection (j) of this section. The current CCN holder must select the independent appraiser by the 21st calendar day after the date of the order determining that the application is administratively complete. The municipality must pay the independent appraiser's costs. The independent appraiser must file its appraisal with the commission by the 70th calendar day after the date of the order determining that the application is administratively complete. The valuation of property under this paragraph is binding on the commission.

(2) For an area annexed by a municipality, the valuation of property that the commission identified in the interim order issued under subsection (j) of this section must be determined by one or more independent appraisers under the process set forth in this paragraph. All independent appraisers must be limited to appraising the property that the commission identified in the interim order issued under subsection (j) of this section. All independent appraisers must be qualified individuals or firms.

(A) If the current CCN holder and the municipality can agree on an independent appraiser within ten calendar days after the application is found administratively complete, the agreed-upon independent appraiser must make a valuation of the property that the commission identified in the interim order issued under subsection (j) of this section.

(i) The agreed-upon independent appraiser must file its appraisal with the commission by the 70th calendar day after the date of the order determining that the application is administratively complete.

(ii) A valuation of property under this subparagraph is binding on the commission.

(B) If the current CCN holder and the municipality cannot agree on an independent appraiser within ten calendar days after the application is found administratively complete, the municipality must notify the serving CCN holder in writing of the failure to agree.

(i) If the parties still cannot agree within 11 calendar days of the written notification, on the 11th day, the current CCN holder and the municipality must each file with the commission a letter appointing a qualified individual or firm to serve as an independent appraiser.

(I) Within 10 business days of their appointment, the independent appraisers must meet to reach an agreed valuation of property that the commission identified in the interim order issued under subsection (j) of this section.

(II) If the independent appraisers reach an agreed valuation of property, the agreed valuation under this subclause is binding on the commission.

(ii) If the appraisers cannot agree on a valuation before the 16th business day after the date of their first meeting under this subsection, then both parties must file separate appraisals by that date, and either the current CCN holder or the municipality must petition the commission to appoint a third appraiser to reconcile the two appraisals.

(I) The commission may delegate authority to appoint the third appraiser.

(II) The third appraiser must file an appraisal that reconciles the two other appraisals by the 80th calendar day after the application is found administratively complete.

(III) The third appraiser's valuation may not be less than the lower or more than the higher of the two original appraisals filed under subparagraph (B)(ii) of this paragraph.

(IV) A valuation of property under this clause is binding on the commission.

(C) The current CCN holder and the municipality must each pay one-half of the costs of all of the appraisers appointed under this paragraph. Payment must be made directly to the appraisers, and proofs of payment must be separately filed by the current CCN holder and the prospective retail public utility within 30 calendar days of the date of the invoice.

(o) Action after receipt of appraisals.

(1) An order incorporating the valuation determined under subsection (n) of this section must be issued by the 90th calendar day after the application is found administratively complete.

(2) The commission must deny the application if the municipality fails to demonstrate compliance with the TCEQ's minimum requirements for public drinking water systems. This paragraph does not apply to a municipality that does not own a public drinking water system.

(3) If the commission does not deny the application, the commission must do the following:

(A) determine what property, if any, is impaired property or requested property;

(B) determine the monetary amount that is adequate and just to compensate the current CCN holder for any such impaired property and requested property;

(C) require the municipality or franchised utility to file a report verifying that the full amount of just and adequate compensation has been paid to the former retail public utility. The report must be filed in the same docket in which compensation was awarded within 30 days of payment of compensation; and

(D) grant single certification to the municipality or franchised utility.

(4) The granting of single certification must be effective on the date that:

(A) the municipality or franchised utility pays adequate and just compensation under a court order;

(B) the municipality or franchised utility pays an amount into the registry of the court or to the current CCN holder under TWC §13.255(f); or

(C) the Travis County district court's judgment becomes final, if the court's judgment provides that the current CCN holder is not entitled to any compensation.

(5) The commission's order does not transfer any property, except as provided under subsection (u) of this section. Any other transfer of property under this section must be obtained only by a court judgment rendered under TWC §13.255(d) or (e).

(6) A presiding officer may issue an order under this section. Any such order must be the final act of the commission subject to motions for rehearing under the commission's rules.

(p) Appeal to the commission, district court, district court judgment, and transfer of property.

(1) A retail public utility that is aggrieved by the final order of the commission may file an appeal with the commission in a separate hearing within 7 days after the final order is issued. A retail public utility must file an appeal with the commission before filing an appeal with the district court.

(2) Under TWC §13.255(e), any party that is aggrieved by a final order of the commission under this section may file an appeal with the district court of Travis County within 30 days after the order becomes final.

(3) Under TWC §13.255(d), if the commission's final order is not appealed within 30 days, the municipality may request the Travis County district court to enter a judgment consistent with the commission's order.

(q) Withdrawal of application for single certification. A municipality or a franchised utility may withdraw an application for single certification without prejudice at any time before a court judgment becomes final, provided that the municipality or the franchised utility has not taken physical possession of property owned by the current CCN holder or made payment for the right to take physical possession under TWC § 13.255(f).

(r) Additional requirements regarding certain current CCN holders. The following subsection applies to proceedings under this section in which the current CCN holder meets the criteria of subsection (a)(3)(B) of this section.

(1) The commission or a court, as appropriate, must determine that the service provided by the current CCN holder is substandard or its rates are unreasonable in view of the current CCN holder's reasonable expenses.

(2) If the municipality abandons its application, the commission is authorized to award to the current CCN holder its reasonable expenses incurred to participate in the proceeding addressing the municipality's application, including attorney's fees.

(3) Unless the current CCN holder otherwise agrees, the municipality must take all of the current CCN holder's personal and real property that is used and useful to provide service or is eligible to be deemed so in a future rate case.

(s) Notice of single certification. Within 60 days of a transfer of property under a court judgment, the municipality or franchised utility must provide written notice to each customer within the service area that is now singly certificated. The written notice must provide the following information: the identity of the municipality or franchised utility, the reason for the transfer, the rates to be charged by the municipality or franchised utility, and the effective date of those rates.

(t) Provision of service.

(1) A municipally owned utility or a franchised utility may provide service to all or a portion of an incorporated or annexed area on one of the following dates:

(A) the date that the commission incorporates the terms of an executed agreement filed with the commission under subsection (d)(3) of this section into the CCNs of the municipality, current CCN holder, and franchised utility, if applicable; or

(B) the date that the municipality or franchised utility:

(i) pays adequate and just compensation under court order, or

(ii) pays an amount into the registry of the court or to the current CCN holder under TWC §13.255(f).

(2) If the court judgment provides that the current CCN holder is not entitled to any compensation, the grant of single certification must go into effect when the court judgment becomes final.

(u) Additional conditions.

(1) If the current CCN holder did not agree in writing to a revocation or amendment sought under this section, then an affected retail public utility may request that the revocation or amendment be conditioned on the following:

(A) ordering the municipality or franchised utility, as applicable, to provide service to the entire service area of the current CCN holder; and

(B) transferring the entire CCN of the current CCN holder to the municipality or franchised utility, as applicable.

(2) The commission must order the municipality or franchised utility, as applicable, to provide service to the entire service area of the current CCN holder if the commission finds that the current CCN holder will be unable to provide continuous and adequate service at an affordable cost to the current CCN holder's remaining customers.

(A) The commission must order the municipality or franchised utility, as applicable, to provide continuous and adequate service to the remaining customers at a cost comparable to the cost of that service to the municipality's or franchised utility's other customers and must establish the terms under which service must be provided.

(B) The commission may order the following terms:

(i) transfer of debt and other contract obligations;

(ii) transfer of real and personal property;

(iii) establishment of interim service rates for affected customers during specified times; and

(iv) other provisions necessary for the just and reasonable allocation of assets and liabilities.

(3) The municipality or franchised utility, as applicable, must not charge the affected customers any transfer fee or other fee to obtain service, except:

(A) the municipality's or franchised utility's usual and customary rates for monthly service, or

(B) interim rates set by the commission, if applicable.

(4) If the commission orders the municipality or franchised utility, as applicable, to provide service to the entire service area of the current CCN holder, the proceeding must not be referred to SOAH for a hearing to determine the impaired property or requested property, and the commission must not order compensation to the current CCN holder.

The agency certifies that legal counsel has reviewed the adoption and found it to be a valid exercise of the agency's legal authority.

Filed with the Office of the Secretary of State on May 29, 2026.

TRD-202602246

Katelyn Lewis

Projects Coordinator

Public Utility Commission of Texas

Effective date: June 18, 2026

Proposal publication date: April 10, 2026